| No | Project Code | Start Date | Due Date | End Date | Duration | Note | Status | Volume |
|---|---|---|---|---|---|---|---|---|
| 01 | 5478B | 14 Aug 2026 | 08 Aug 2026 | 10 Aug 2026 | Team 5 Days |
SESUAI
|
DONE
|
9,47 |
| 02 | P-020 (5) 2 | 14 Aug 2026 | 08 Aug 2026 | 05 Aug 2026 | Team 5 Days |
SESUAI
|
DONE
|
1,00 |
| 03 | 5616B | 14 Aug 2026 | 08 Aug 2026 | 07 Aug 2026 | Team 5 Days |
SESUAI
|
DONE
|
2,88 |
| 04 | 5490B | 14 Aug 2026 | 08 Aug 2026 | 06 Aug 2026 | Team 5 Days |
SESUAI
|
DONE
|
0,82 |
| Total Volume | 14,17 | |||||||